2021 Pool “Restoration”
During the Summer of 2020 the COVID-19 pandemic was in full swing and Becky and I were noticing that the shallow end of our pool was significantly lower than it had been the year before. There was about a 4” or 5” difference in water level between the deep end and shallow end because the walls of our on-ground pool were sinking.
After much discussion and back-and-forth we made the decision to keep the pool and invest the time and money into fixing it.
This page documents our adventure through photos and commentary as the pool techs came in and returned our pool to factory settings.
Step 1 - Deck Demolition
On September 11, 2021 my cousin, my parents, my sister and brother-in-law all showed up to help us remove the deck around the pool. With all hands on deck (no pun intended!) it took only one day to remove the decking and patio stones!
Since all of the boards were rotten and unsalvageable we ordered a large dumpster bin. Although the bin was quite big we cut all the boards into smaller chunks to save room. I’m glad we took the extra time to do this as it really helped pack the bin nice and tight.
Step 2 - What’s behind the curtain?
The Monday after we took down the deck, the pool experts called us and asked if they could start that same day!
The original plan at this point was to have them come in and raise the one end panel about 4 inches, put in some stairs, and replace the liner.
After they removed the liner and measured the trueness of the pool’s levelness, there was a lot more work that needed to be done…
Step 3 - Dig Deep
The next step in our adventure was to dig around the sides of the pool so they could be levelled and a proper concrete base could be pored. Unfortunately there is no access to our backyard for any small machinery so all of the digging had to be done by hand.
(Left) Logan thought it would be a good time to go for a swim!
Step 4 - Levelling Up
After digging out the sides the pool experts levelled each side to within an inch or two of level.
Step 5 - Goodbye Floor
This was very hard labour… for the pool experts as they jackhammered the pool floor and had to carry out the pieces in buckets to the trailer. We live on the side of a hill and so they had to climb the equivalent of 2 to 3 flights of stairs to remove this cement - not including the distance from the pool bottom itself!
Step 6 - New Stairs!
One of the original goals of this project was to install a set of built-in stairs in the pool. This was an exciting day watching them install these stairs.
Step 7 - Solidify the foundation with lots of concrete!
This was by far the most amazing day of the pool work. As I’ve mentioned before we live on the side of a hill and there is a flight of stairs from the driveway to the back yard and then the pool is a little further downhill. All the concrete had to be manually moved from the end of the driveway to the pool using wheelbarrows.
They used three wheelbarrows in total. One person would take a barrow full from the pump truck along the side of the house where they would pour it over the side of the ramp into a second wheelbarrow. This second person would then wheel it down the backyard, up the ramp to the shallow end, and pour it into a third wheelbarrow sitting in the shallow end of the pool. Finally this third person would wheel the barrow into the deep end where they would apply it to the pool floor.
Overall there was 9 cubic yards of concrete moved around and poured for the foundation and pool floor.
Step 8 - Plumbing and drainage
After the concrete was poured, weeping tile (the black tube in the pictures) was installed to help drain rain water away from the pool. It was buried in gravel to further help with drainage and help prevent the pool from sinking.
Step 9 - Pool Flooring
The pool floor is composed of two layers. The foundation layer (see prior step) is concrete with a high slump value, and the topcoat which is a special ‘smoother’ mix of grout.
The grout floor was mixed using a concrete mixer in our driveway and then delivered using the ‘wheel barrow’ method similar to the concrete delivery method.
They started in the deep end and worked their way to the shallow. Unfortunately I wasn’t able to get a picture of the most important step… how did they apply mud to that last strip up the middle of the deep-end? (See pictures below.)
Step 10 - Backfill
With the walls all cemented in, the floor completed and all the plumbing done, it’s time to put all that dirt that was moved back.
Gravel was wheel barrowed in and covered the weeping tile that was laid down around the base of the pool and then was covered with landscape fabric. The dirt was then shoveled over top.
Step 11 - The Pool Liner
Finally the moment we’ve been waiting for, the pool liner.
The pool floor was still a little rough and needed to be sanded. Then the liner was installed. Unfortunately I didn’t get any pictures of the liner being installed.
The liner is connected and ‘sealed off’ at the top. Two very large fans suck the pool liner up against the floor and walls while the water is filled to avoid wrinkles etc.